Typical Timeline for 2000㎡ Steel Structure Workshop
1. Foundation curing: 3–4 weeks (weather dependent)

2. Steel erection: 10–15 working days with 6–8 workers + crane

3. Enclosure: 7–10 working days

4. Total on-site: 3–4 weeks after foundation ready