Typical Timeline for 2000㎡ Steel Structure Workshop - Knowledge
1. Foundation curing: 3–4 weeks (weather dependent) 2. Steel erection: 10–15 working days with 6–8 workers + crane...

2. Steel erection: 10–15 working days with 6–8 workers + crane
3. Enclosure: 7–10 working days
4. Total on-site: 3–4 weeks after foundation ready